Your schedule analysis has shown that your project has a high likelihood of experiencing a schedule overrun. You know this because the cumulative EV is much ().
A.higher than the cumulative AC
B.higher than the cumulative PV
C.lower than the cumulative PV
D.lower than the cumulative CPI