Due to cuts in funding, your project has been terminated. The scope verification process ().

A.should be delayed until the project is completed
B.should determine the correctness of the work results
C.should establish and document the level and extent of completion
D.will form the basis of the project audit

<上一题 目录 下一题>
热门试题

单项选择题All of the following is true for a project baseline EXCEPT ().

A.it is the original approved plan
B.it includes approved scope changes
C.it is useful in detecting project variances
D.it is useful in preparing the WBS

单项选择题Your technical team leader, Ted, proposed an action that would overall project quality with a minor cost increase. The project control officer, Sun Ha, recommended an approach that would shorten the project schedule, but reduce product features. Increasing quality and accelerating the schedule are critical form your point of view. Although you believe that Ted and Sun Ha could learn from each other, they typically like to agree to disagree. You need a conflict resolution method that provides a long-term resolution. You decide to use which one of the following approaches ?()

A.Confronting
B.Problem solving
C.Compromise
D.Smoothing