两个投资项目(项目A和项目B)的相关数据如下表所示,且两项目的必要回报率均为14%。试根据这些条件解答问题。
项目A和项目B的相关数据
|
| |
项目A |
项目B |
初始成本 年限 现金流 |
2800万美元 2 1800万美元/年 |
5500万美元 3 2500万美元/年 |
|
Oriency Company is considering a project that requires $56 million
cash outlay and is expected to produce cash flow of $15 million per year for the
next three years. Oriency’s tax rate is 35%, and the before-tax cost of debt is
6%. The current share price of Oriency’s stock is $27 and the expected dividend
next year is $1.8 per share. Oriency’s expected growth rate is 2%. Assume that
Oriency finances the project with 70% equity and 30% debt, and the flotation
cost for equity is 3%. The appropriate discount rate is the weighted average
cost of capital (WACC). Which of the following choices is closest to the dollar
amount of the flotation costs and the NPV for project
dollar amount of the flotation costs NPV for project
① $1176000
$2003910
② $1176000
$3435268 ③
$1680000
$3435268
A. ①
B. ②
C. ③