The Scope Management Plan is included in which of the following document

A. Project plan.
B. The Work Breakdown Structure.
C. The Scope Statement.
D. Project Specification.
<上一题 目录 下一题>
热门试题

单项选择题A project control system ______.

A. monitors and controls the project’s schedule, costs, scope, budgets, etc.
B. is a mechanism which reacts to the current project status in order to ensure accomplishment of project objectives
C. is only needed on large "mega" projects
D. is a system for controlling and executing project documentation in a uniform and timely manner

单项选择题All of the following rules are true about the lowest level WBS work packages EXCEPT work package ______.

A. can be completed without interruption in one location
B. can be confidently estimated
C. must be assigned to only one person
D. must be completed with 80 hours