The PM and project team have completed decomposition and have verified
scope, when the marketing department makes a minor change to the product
functionality to improve its appeal to the end customer. The PM and the project
team ______.
A. refuses to accept the change since the scope has been veri{ied
B. modifies the WBS and the decomposition
C. accepts the change and incorporates it into the WBS, modifying the budget
and the schedule and assigning accountability to the marketing team
D. proceeds per the change process